Summary0008131: Share Build between TPs on same Project
DescriptionIt's not possible to share same build inside same project (almost) to all TP.

Aren't present a build "copy/link/export/import " functionalities.
TagsNo tags attached.
Database (MySQL,Postgres,etc)MySQL
Browser
PHP Version
TestCaseID
QA Team - Task Workflow Status
Attached Files

- Relationships

-  Notes
(0027011)
fman (administrator)
2017-11-11 15:41

unfortunately your explanation is far from clear for me.
without a better detailed explanation no action can be taken
(0027013)
decicco (reporter)
2017-11-13 07:35

HI,
    builds is strictly related to TestPlan : to use same build on several TestCase not in same plan, i have to copy into test plan: why not share build into alle testproject.

Just to explain : if i have tihis situation

Project
    - Plan 1 - TestSuiteA, TCase1...
    - plan 2 - TestSuiteB, TCase2...
...
    - plan N

buildX on Plan1

--- i cannot launch TCase2 on buildX only if a copy the build on plan2 (or in all plan i want to use)....

Hope i clear a little more...
(0027014)
fman (administrator)
2017-11-13 08:58

your details are still far from clear.
IMHO you have a confusion with build concept

TEST CASE are LINKED to test plans no to builds, builds are used to assign testers.
If you want to testplan have same test cases you need to link test case to both test plans
(0027015)
decicco (reporter)
2017-11-13 15:57

thanks for your patience!!!

When i create a build (to execute a specific TCase) i have to create build rel. inside same TPlan related to TCase "Each build is related to the active Test Plan."

I may define a different TCase into another TPlan :
i would test a SW rel. (our "build") on different TPlan (example : secure instead of performance), with different TCase.

Any suggestion?

- Issue History
Date Modified Username Field Change
2017-11-10 08:44 decicco New Issue
2017-11-11 15:41 fman Note Added: 0027011
2017-11-11 15:43 fman Assigned To => fman
2017-11-11 15:43 fman Status new => feedback
2017-11-13 07:35 decicco Note Added: 0027013
2017-11-13 07:35 decicco Status feedback => assigned
2017-11-13 08:58 fman Note Added: 0027014
2017-11-13 15:57 decicco Note Added: 0027015