ID | Project | Category | View Status | Date Submitted | Last Update | ||||
0006435 | TestLink | Build Management | public | 2014-07-10 06:15 | 2014-12-06 16:10 | ||||
Reporter | sameerali | ||||||||
Assigned To | fman | ||||||||
Priority | normal | Severity | feature request | Reproducibility | always | ||||
Status | closed | Resolution | fixed | ||||||
Platform | All | OS | All | OS Version | All | ||||
Product Version | 1.9.10 (2014 Q1 - bug fixing) | ||||||||
Fixed in Version | 1.9.13 (2015 #1) | ||||||||
Summary | 0006435: Build assignment to made available at execution time | ||||||||
Description | Test case assignment is generally a restricted activity which happens at test planning and build generation happens once or twice a week hence each time test case assignment has to be done whenever a new build has arrived, it will be good if the workflow is like this: Test case assignment is independent of build. Build parameter should be included at test case execution time through a drop down menu from the available active/open builds. | ||||||||
Tags | No tags attached. | ||||||||
Database (MySQL,Postgres,etc) | MySQL | ||||||||
Browser | mozilla | ||||||||
PHP Version | PHP 5.5.13 | ||||||||
TestCaseID | |||||||||
QA Team - Task Workflow Status | READY FOR TESTING | ||||||||
Attached Files | |||||||||
![]() |
|
(0021229) fman (administrator) 2014-07-10 07:41 |
unfortunately your explanation is not clear for me. Please provide a very detailed example |
(0021237) sameerali (reporter) 2014-07-10 08:18 |
Sorry for not being so clear in putting my words, so let me put it once again. The current implementation of build management is per test-plan and a build is assigned per test case at the time of test case assignment to individual tester/users which is having a limitation, in case a new build arrival rate is high in such a case the test manager/lead has to re-assign the test cases each time a new build has arrived thereby increasing the overhead of re-assigning the test-cases with arrival of each build. In order to address this I am proposing a solution as below: The build selection per test-case should be done at the time of test-case execution in place of test-case assignment. The build can be selected from a drop-down menu from the available active builds. I hope I am clear this time. |
(0021241) fman (administrator) 2014-07-10 10:06 |
>> The current implementation of build management is per test-plan and a build >>is assigned per test case at the time of test case assignment to individual >>tester/users which is having a limitation, in case a new build arrival rate is >>high in such a case the test manager/lead has to re-assign the test cases each >>time a new build has arrived thereby increasing the overhead of re-assigning >>the test-cases with arrival of each build solution is create build from previous build copying tester assignment |
(0021242) sameerali (reporter) 2014-07-10 11:57 |
Thanks fman, got the solution, you can close the bug. |
(0021243) fman (administrator) 2014-07-10 11:59 |
Ok, then just to be sure: note 21241 is solution for you ? |
![]() |
|||
Date Modified | Username | Field | Change |
2014-07-10 06:15 | sameerali | New Issue | |
2014-07-10 07:41 | fman | Note Added: 0021229 | |
2014-07-10 08:18 | sameerali | Note Added: 0021237 | |
2014-07-10 10:06 | fman | Note Added: 0021241 | |
2014-07-10 11:57 | sameerali | Note Added: 0021242 | |
2014-07-10 11:59 | fman | Note Added: 0021243 | |
2014-12-06 16:10 | fman | QA Team - Task Workflow Status | => READY FOR TESTING |
2014-12-06 16:10 | fman | Status | new => closed |
2014-12-06 16:10 | fman | Assigned To | => fman |
2014-12-06 16:10 | fman | Resolution | open => fixed |
2014-12-06 16:10 | fman | Fixed in Version | => 1.9.13 (2015 #1) |